PMP考试每天一练-2020年PMP考试练习题111

转载者:PMP团购网      发布时间:2020/8/24        点击: 1488

PMP考试练习题一:

During the project’s system testing phase, the testing team discovers the reoccurrence of many defects that were previously closed. What should the project manager do next?

A.Ask the technical lead why the defect rate suddenly increased

B.Verify that the testing team is using the proper testing methodology

C.Analyze the reasons for the high defect rate with the assistance of the testing teams

D.Submit a change request to eliminate the defects

在项目的系统测试阶段,测试团队发现之前已关闭的许多缺陷再次发生。项目经理下一步该怎么做?

A.询问技术主管缺陷率突然上升的原因

B.确认测试团队使用的是正确的测试方法

C.在测试团队的协助之下,分析发生高缺陷率的原因

D.提交变更请求减少缺陷

PMP考试答案解析:缺陷再次发生,应该去分析原因。

PMP考试参考答案:C

PMP考试练习题二

During project execution, the sponsor leaves the company. What should the project manager do next?

A. Perform integrated change control

B. Decentralize project authority and decision-making

C. Produce a project status report

D. Conduct a stakeholder analysis

在项目执行期间,项目发起人离开公司。项目经理接下来应该怎么做?

A.执行整体变更控制

B.分散项目权利和决策制定。

C.制作一份项目状态报告。

D.进行干系人分析。

PMP考试答案解析:发起人离开公司,对项目的影响很大。通过对干系人进行分析,识别出干系人的利益、期望和影响。

PMP考试参考答案:D

阅读本文的人还阅读了:
pmp报考条件是什么?
pmp报名条件是什么?
pmp考试需要什么学历?
南昌PMP考试地点在哪里?
PMP证书含金量有多少?
PMP考试时间和考试费用是多少?
pmp教材第六版pdf下载
pmp远程好面授好,谁知道?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库