PMP考试每天一练-2020年PMP考试练习题110

转载者:PMP团购网      发布时间:2020/8/21        点击: 1225

PMP考试练习题一:

During the implementation of an information technology(IT) development project, severe weather conditions in country X prevent developers from travelling to the IT company’s offices. To minimize the impact of this risk, the project manager transfers the work to another software development team based in country Y.The project manager’s actions are an example of which risk response strategy?

A.Risk mitigation

B.Risk transference

C.Management reserve allocation

D.Contingency response

在执行一个信息技术(IT)开发项目过程中,X国恶劣的天气情况让开发人员不能前往IT公司的办公室。为了尽可能减少该风险的影响,项目经理将工作转移给Y国的另一个软件开发团队。项目经理的行动属于哪一种风险应对策略的范例?

A.风险减轻

B.风险转移

C.管理储备分配

D.应急应对

PMP考试答案解析:题干说为了尽可能“减少”该风险的影响,PM将工作转移给Y国的另一个软件开发团队。这是减轻风险影响,选用更可靠的供应商。

PMP考试参考答案:A

PMP考试练习题二

During the approval of a project management plan, the project sponsor identifies an external risk overlooked by the project team. What should the project manager do?

A. Plan the risk response

B. Identify risk and mitigation activities

C. Add the risk to the risk register and ask the project team to review the project management plan to consider ist significance

D. Ask the project sponsor to submit a formal change request and present to other stakeholders.

在批准项目管理计划期间,项目发起人识别到一个被项目团队忽略的外部风险。项目经理应该怎么做?

A.制定风险应对计划

B.识别风险和风险减轻活动

C.将风险添加进风险登记册,并要求项目团队审查项目管理计划,考虑该风险的重要性

D.要求项目发起人提交一份正式的变更请求,并提供给其他项目干系人

PMP考试答案解析:识别到新风险后,首先应该更新进风险登记册。

PMP考试参考答案:C

阅读本文的人还阅读了:
pmp报名条件是什么?
考pmp需要什么条件?
昆山PMP考试地点在哪里?
PMP证书含金量浅析
PMP考试日期是什么?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库