PMP考试练习题一:

While acquiring resources for a strategic project, the project manager discovers that a key resource will not be available to perform a project task. Assuming the task was not planned on the critical path, what strategy should be used to mitigate this issue

A.Attempt to reduce the project scope

B.Assign a less-skilled resource on the project and increase the task duration

C.Obtain permission to work on the weekends

D.Extend the project’s end-data and resolve the issue at a later project stage

在为一个战略项目招募资源时,项目经理发现一名关键资源将不能执行项目任务。假设该任务的计划并不处于关键路径上,应使用什么战略来减轻这个问题?

A.试图减少项目范围

B.分配一个技能稍差的资源在项目上并增加该任务的持续时间

C.获得在周末工作的许可

D.延长项目结束的时间并在项目后期阶段解决这个问题

PMP考试答案解析:该任务不在关键路径,有时差,那么可以延期,可以安排技能差的资源并适当增加该任务持续时间。选项A和D是回避。

PMP考试参考答案:B

PMP考试练习题二

A project manager identifies and documents project roles, responsibilities, and skills. Which tool or technique should the project manager use to define the human resource management plan?

A. Organizational charts and skill descriptions

B. Ground rules

C. Interpersonal skills

D. Organizational charts and position descriptions

项目经理识别并记录项目角色、职责和技能。项目经理应使用哪一项工具或技术来定义人力资源管理计划?

A.组织图和技能描述

B.基本规则

C.人际关系技能

D.组织图和岗位描述

PMP考试答案解析:规划人力资源管理的工具。

PMP考试参考答案:D

阅读本文的人还阅读了:
pmp报考条件是什么?
pmp报考条件及费用?
pmp报名条件是什么?
pmp报考条件必须参加培训吗?
考pmp需要什么条件?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库