PMP考试每天一练-2020年PMP考试练习题106
PMP考试练习题一: In which stage of team development do team members begin to work together and adjust work habits and behaviors that support the team? A.Forming B.Storming C.Performing D.norming 团队成员开始一起工作并调整支持团队的工作习惯和行为属于团队发展的哪一个阶段? A.形成阶段 B.震荡阶段 C.成熟阶段 D.规范阶段 PMP答案解析:在规范阶段,团队成员开始协同工作,并调整各自的工作习惯和行为来支持团队,团队成员开始相互信任。 PMP参考答案:D PMP考试练习题二 A project manager finds that a project's planned value (PV) is US$120 million, its earned value (EV) is US$6 million, and its actual cost (AC) is US$60 million. Which of the following describes the project's completion status? A. The project is ahead of schedule and on budget B. There is not enough information to calculate the cost performance index (CPI) C. The project is behind schedule and over budget D. The project is behind schedule and on budget 项目经理发现项目的计划价值(PV)为1.2亿美元,净值(EV)为600万美元,实际成本(AC)为6000万美元。下列哪一项描述了项目的完成状态? A.项目超前于进度,并符合预算 B.信息不足,无法计算成本绩效指数(CPI) C.项目落后于进度,并超出预算 D.项目落后于进度,但符合预算 PMP答案解析:SPI=600/12000=0.05进度落后,CPI=600/6000=0.1成本超支。根据干系人的职权(权力)大小及对项目结果的关注(利益)程度进行分类,以便管理好不同干系人。 PMP参考答案:C |