PMP考试每天一练-2020年PMP考试练习题105

转载者:PMP团购网      发布时间:2020/8/10        点击: 1317

PMP考试练习题一:

During a routine project update, the project sponsor stakes that the project schedule is unacceptably long. The project manager agrees to provide a proposal to accelerate the schedule.This is an example of which of the following?

A.PUSH COMMUNICATION

B.INTERACTIVE COMMUNICATION

C.Success modeling

D.Timeline adjustment

在一次例行项目更新中,项目发起人称项目进度时间之长不可接受。项目经理同意提供一份加快该进度计划的建议书。这属于下列哪一项的实例?

A.推式沟通

B.交互式沟通

C.成功模型

D.时间线调整

PMP答案解析:有来有去,交互式沟通。

PMP参考答案:B

PMP考试练习题二

While working with the project team to prepare a network diagram, the project manager notices a series of activities can be performed in parallel, but must be finished in a specific sequence.What activity sequencing method is required?

A, Operational diagramming method

B. Precedence diagramming method

C. Critical path method

D. Arrow diagramming method

与项目团队一起合作制作一份网络图的时候,项目经理注意到一系列活动能够并行执行,且必须按特定顺序完成。这需要哪一种活动排序方法?

A.操作绘图法

B.紧前关系绘图法

C.关键路径法

D.箭头绘图法

PMP答案解析:排列活动顺序的工具,紧前关系绘图法PDM。

PMP参考答案:B

阅读本文的人还阅读了:
PMP考试有题库吗?
重庆PMP考试地点在哪里?
杭州PMP培训哪个好?几大杭州PMP培训机构对比
PMP考试报名费是多少?
PMP考试费用多少钱?
PMP考试是英文,还是中文?
PMP考试有什么科目?
PMP考试三个月来得及吗?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库