PMP考试练习题一: During a routine project update, the project sponsor stakes that the project schedule is unacceptably long. The project manager agrees to provide a proposal to accelerate the schedule.This is an example of which of the following? A.PUSH COMMUNICATION B.INTERACTIVE COMMUNICATION C.Success modeling D.Timeline adjustment 在一次例行项目更新中,项目发起人称项目进度时间之长不可接受。项目经理同意提供一份加快该进度计划的建议书。这属于下列哪一项的实例? A.推式沟通 B.交互式沟通 C.成功模型 D.时间线调整 PMP答案解析:有来有去,交互式沟通。 PMP参考答案:B PMP考试练习题二 While working with the project team to prepare a network diagram, the project manager notices a series of activities can be performed in parallel, but must be finished in a specific sequence.What activity sequencing method is required? A, Operational diagramming method B. Precedence diagramming method C. Critical path method D. Arrow diagramming method 与项目团队一起合作制作一份网络图的时候,项目经理注意到一系列活动能够并行执行,且必须按特定顺序完成。这需要哪一种活动排序方法? A.操作绘图法 B.紧前关系绘图法 C.关键路径法 D.箭头绘图法 PMP答案解析:排列活动顺序的工具,紧前关系绘图法PDM。 PMP参考答案:B |