PMP考试每天一练-2020年PMP考试练习题87

转载者:PMP团购网      发布时间:2020/7/3        点击: 1741

PMP考试练习题一:

A project manager oversees a construction project which involves demolishing an old building and constructing a new building in its place. The project manager obtains the owner’s name of the adjacent lot where some construction vehicles may inadvertently pass through What should the project manager do first?

A.Include the lot owner in the project team meetings

B.Add the lot owner’s name to the communications management plan

C.Build the project schedule outside of normal business hours

D.Add the lot owner’s name to the stakeholder register

项目经理管理一个涉及拆除旧建筑并在原地建设新建筑的项目。项目经理获得一些施工车辆可能会无意中经过的临近地段业权人姓名。项目经理首先应该做什么?

A.将该地段业权人包含在项目会议中

B.将该地段业权人姓名添加到沟通管理计划中

C.创建在正常工作时间之外的项目进度计划

D.将该地段业权人姓名添加进干系人登记册中

PMP答案解析:该地段业权人也是项目的干系人,应该更新进干系人登记册。

PMP参考答案:D

PMP考试练习题二

During project execution, the project manager learns that the project sponsor will send a team of external consultants to review whether the project activities are on track to meet the project requirements and timeline. This is an example of which of the following types of action?

A. Corrective

B. Reactive

C. Preventive

D. Proactive

在项目执行期间,项目经理了解到项目发起人将派遣由外部顾问组成的团队审查项目活动是否符合进度,满足项目要求和时间线。这属于下列哪一项措施的实例?

A.纠正措施

B.反应措施

C.预防措施

D.主动措施

PMP答案解析:执行期间,发起人派遣外部顾问团队审查活动是否符合要求,这是提前预防。

PMP参考答案:C

阅读本文的人还阅读了:
PMP证书含金量有多少?
在国内PMP有多少含金量?
pmp考试教材?
PMP考试含金量?
pmbok第六版免费下载
pmbok第六版英文版 pdf
pmp培训远程还是面授好?
pmp培训远程还是面授,怎么选?

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库