PMP考试每天一练-2020年PMP考试试题83
PMP考试试题一: To keep a critical component in operation, the project manager obtains more reliable server hardware. This increases the server’s operational complexity.What type of risk is the project manager assuming? A.Primary B.Secondary C.Accepted D.residual 为了保证一个关键组件稳定运行,项目经理获得更可靠的服务器硬件。但这会增加服务器运作复杂性。项目经理承担的是什么风险类型? A.主要风险 B.次生风险 C.已接受风险 D.残余风险 PMP答案解析:次生风险是由实施风险应对措施导致的新风险。 PMP参考答案:B PMP考试试题二 During a project's execution phase, a change is approved which requires additional resources with skills not currently available within the project. What asset should be revised to define the new resource requirements? A. Project organization chart B. RACI chart C. Staffing management plan D. Resource calendar 在项目执行阶段,一项变更已获得批准,但要求具有当前项目团队中没有的额外技能资源,应修改哪项资产以便定义新的资源需求? A.项目组织图 B.RACI图 C.人员配备管理计划 D.资源日历 PMP答案解析:人员配备管理计划里面涉及了人员招募、培训需要等等。 PMP参考答案:C |