PMP考试每天一练-2020年PMP考试试题81
PMP考试试题一: A less experienced project coordinator has joined an organization. This coordinator does not have the same depth of experience in the organization as other staff, but leads by using persuasion and a commitment to the work.The coordinator demonstrates which type of power? A.Charismatic B.Coercive C.Legitimate D.expert 一位经验不足的项目协调员加入组织。该协调员在组织中的经验丰富程度不如其他员工,但其使用劝说和对工作的投入来领导项目。该协调员证明了什么权利类型? A.领袖权利 B.强制权利 C.合法权利 D.专家权利 PMP答案解析:合法权力也叫正式权力,由章程授予的权力,由项目经理职位而定的权力。没有领袖权力的说法,排除A;B强制权力也叫惩罚权力,题干并没有提到惩罚某人,排除B;经验不足,排除D。 PMP参考答案:C PMP考试试题二 A project manager finds that a project's cost performance index (CPI) is 1.2 and its schedule performance index (SPI) is 0.79. Which of the following actions should the project manager pursue? A. Crashing B. Fast tracking C. Delphi technique D. Monte Carlo simulation 项目经理发现项目的成本绩效指数(CPI)为1.2,进度绩效指数(SPI)为0.79,项目经理应采取下列哪一项行动? A.赶工 B.快速跟进 C.德尔菲技术 D.蒙特卡洛模拟 PMP答案解析:成本结余、进度落后,应该赶工。 PMP参考答案:A |