PMP考试每天一练-2020年PMP考试试题80

转载者:PMP团购网      发布时间:2020/6/19        点击: 1604

PMP考试试题一:

Midway through a project to upgrade a company’s system. It is determined that there is an incompatibility between the existing hardware and the newly installed equipment.What should the project manager do first?

A.Identify the team member responsible for the equipment procurement error

B.Perform a quantitative risk analysis

C.Document, monitor, and track the issue in the issue log

D.Perform a qualitative risk analysis

在一个升级公司系统的项目中途,确定现有硬件和新安装设备之间存在一个不兼容处。项目经理首先应该做什么?

A.找出负责设备采购错误的团队成员

B.执行定量风险分析

C.在问题日志中记录、监控和跟踪问题

D.执行定性风险分析

PMP答案解析:“确定”现有硬件和新安装设备之间存在一个不兼容处,说明不是风险,是个问题。应该在问题日志中记录、跟踪。

PMP参考答案:C

PMP考试试题二

Each time a project component is tested, the component passes user acceptance testing and fulfills all requirements, what process did the project manager implement and execute repeatedly?

A. Control Quality

B. Perform Quality Assurance

C. Configuration Analysis

D. Sponsor Reviews

每次测试项目部件,该部件都通过用户的验收测试并满足所有需求。项目经理反复实施和执行哪一个过程?

A.控制质量

B.执行质量保证

C.配置分析

D.发起人审查

PMP答案解析:达到质量标准,能通过验收测试,这是质量控制。

PMP参考答案:A

阅读本文的人还阅读了:
PMP远程培训多少钱?
pmp远程班的价格贵吗?
pmp远程课程费用大概是多少?
pmp项目管理师是什么?
pmp证书是什么?
PMP考点在哪里?
PMP认证费用多少?
PMP认证多少钱?


PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库