PMP考试试题一:

A project is staffed with qualified team members. However, in the project’s fifth month, the project falls behind schedule and is over budget. The team’s morale is low after two team members leave the project. Team members do not share information and ther4e is a general atmosphere of mistrust。To avoid this situation, the project manager should have done which of the following?

A.Empowered team members and encouraged individual problem-solving

B.Focused on the team as a whole, created a cohesive team culture with shared vision, and allowed cross-training between team members

C.Improved knowledge and skills of each team member to increase their ability to complete project deliverables on time

D.Instituted a chain of command to clarify the responsibilities of each team member

一个项目的人员都是数个团队的成员。但是,在项目的第五个月,项目落后于进度,并超出预算。在两名团队成员离开项目后,团队士气地下。团队成员之间相互不分享信息,存在普遍不信任的氛围。为避免这种情况,项目经理应该已经完成下列哪一项?

A.授权团队成员并鼓励个人问题解决

B.将团队作为一个整体关注,创造一个具有分享观念的有凝聚力团队文化,允许团队成员之间的交叉培训

C.改善每名团队成员的知识和技能,提高他们按时完成项目可交付成果的能力

D.提出一系列指令,澄清每名团队成员的责任

PMP答案解析:B最完善。

PMP参考答案:B

PMP考试试题二

A project manager is asked to estimate an activity's duration. Using historical information, the project manager learns that this activity has routinely taken 12 days to complete. The project anger’s colleague works on a similar project and performed the activity in 10 days. However, the functional area expert states that, due to challenges on the project, it will take 18 days to complete, IF the project manager uses PERT estimation, what would be the activity’s duration?

A. 12days

B. 12.7days

C. 15.7days

D. 18days

PMP答案解析:三点计算公式(10+4*12+18)/6=12.7。

PMP参考答案:B

阅读本文的人还阅读了:
PMP证书含金量有哪些?
pmp考试含金量多少?
PMP考试骗局?
PMP考试报名官网是什么?
pmbok第六版英文版 pdf
pmp教材第六版pdf下载
pmp远程好面授好,谁知道?
pmp培训远程还是面授好?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库