PMP考试试题一:

A project’s budget to develop and deploy a company’s product is US$10 million. The project manager must plan the project and complete the work within 12 months. After discussing with stakeholders, the project manager evaluates if the product can be developed by internal employees.Which of the following techniques should the project manager use?

A.Make-or-buy analysis

B.Cost benefit analysis

C.Life cycle cost analysis

D.Outsourcing technique

开发并部署公司产品的项目预算为1000万美元。项目经理必须规划项目并在12月内完成。在与干系人讨论之后,项目经理评估是否可以由内部员工开发产品。项目经理应使用下列哪一项技术?

A.自制或外购分析

B.成本-效益分析

C.生命期成本分析

D.外包技术

PMP答案解析:评估由外部或内部员工开发,自制或外购分析。

PMP参考答案:A

PMP考试试题二

Due to unavoidable circumstances, a project is terminated before it is completed. What should the project manager do to close the project?

A. Prepare the change management documentation

B. Prepare formal documentation indicating why the project was terminated

C. Update the benefits realization documentation

D. Reassign the team members

由于不可避免的情况,项目在完工前终止。收尾项目时,项目经理应该做些什么?

A.准备变更管理文档

B.准备正式文档说明项目为何终止

C.更新效益现实文档

D.为团队成员重新分配任务

PMP答案解析:对于完工前终止的项目需要调查原因。

PMP参考答案:B

阅读本文的人还阅读了:
PMP证书含金量是什么?
PMP证书含金量有哪些?
pmp教材第六版pdf下载
pmbok第六版 pdf下载英文版
pmbok6英文版下载
pmbok第六版中文版pdf
pmp培训远程还是面授好?
pmp培训远程还是面授,怎么选?
PMP远程对比面授有哪些优势?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库