PMP考试试题一:

During the monitoring and controlling phase, a client requests that only eight of the 13 originally planned tests be conducted. What should the project manager do next?

A.Ask the client to submit a change request

B.Change the scope baseline

C.Review the risk/reward clauses in the contract

D.Review the penalty clauses in the contract

在监控阶段,一名客户请求只需开展13个原始计划测试中的其中八个。项目经理下一步应该怎么做?

A.让客户提交一份变更请求

B.变更范围基准

C.查看合同中的风险/奖励条款

D.查看合同中的惩罚条款

PMP答案解析:有变更,遵循变更管理流程。

PMP参考答案:A

PMP考试试题二

A project’s total cost is US$200,000. The project management requests a study to verify whether the project will run behind schedule. The project has a 35% chance ofincurring a penalty of US$20,000 due to a delay in completion. There is a 65% chance that the company will earn US$500,000 on the project. What is the expected monetary value?

A. US$118,000

B. US$293,000

C. US$318, 000

D. US$325,000

项目总成本为US$200,000.项目管理办公室要求开展一项研究,来验证项目是否会落后于进度。项目有35%的机会发生因完工延期所导致的US$20,000罚款。还有65%的机会公司将在项目中获利US$500,000。那么预期货币价值是多少?

A. US$118,000

B. US$293,000

C. US$318,000

D. US$325,000

PMP答案解析:EMV=35%*(-20000)+65%*500000=318000

PMP参考答案:C

阅读本文的人还阅读了:
PMP证书含金量高吗?
PMP证书含金量到底是多少?
PMP考试报名官网是什么?
PMP考试科目是什么?
pmbok第6版pdf百度网盘
pmbok第六版电子版

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库