PMP考试每天一练-2020年PMP考试试题50
PMP考试试题一: During the upgrade of a new telecommunications system, the project team discovers the new soft ware patches may cause instability during live operations under certain conditions. After receiving this information, the project manager prepares additional tests.What type of risk response is being performed? A.Acceptance B.Mitigation C.Avoidance D.Transfer 在升级新电信系统当中,项目团队发现新软件补丁可能在特定环境下的有效运行期间造成不确定性,接受到这个信息后,项目经理准备了额外测试。这是执行什么类型的风险应对策略? A.接受 B.减轻 C.回避 D.转移 PMP答案解析:担心可能出错,PM准备了额外测试、多做了额外测试,这是减轻。 PMP参考答案:B PMP考试试题二 The project manager identifies that a finish-to-start dependency for an activity on the critical path is missing. The project schedule was already communicated to the customer. What should the project manager have done to avoid this issue? A. Reviewed the work breakdown structure B. Conducted a schedule network analysis C. Prepared a risk management plan D. Conducted an earned value analysis 项目经理发现关键路径上一项活动的开始到结束依赖关系遗漏了。项目进度计划已经与客户沟通。若要避免这个问题,项目经理应该事先做什么? A.审查工作分解结构 B.进行进度网络分析 C.制定风险管理计划 D.进行挣值分析 PMP答案解析:进行进度网络分析,分析依赖关系。 PMP参考答案:B |