PMP考试试题一:

A project manager prioritizes project risks based on the probability of occurrence and potential of occurrence and potential impact to the project. Which of the following is being performed?

A.Quantitative risk analysis

B.Qualitative risk analysis

C.Schedule network analysis

D.Plan risk analysis

项目经理根据发生概率以及对项目的潜在影响对项目风险排列优先顺序。项目经理正在进行下列哪一项?

A.定量风险分析

B.定性风险分析

C.进度网络分析

D.计划风险分析

PMP答案解析:对风险排列优先顺序,这是在对风险进行定性分析。

PMP参考答案:B

PMP考试试题二

Due to resource constraints, a project manager determines that a portion of the project work must be outsourced, Which of the following inputs are required to ensure the requirements and the timeline are met?

A. Qualified sellers’ list and scope

B. Schedule and scope

C. Cost estimates and performance

D. Cost estimates and schedule

由于资源约束条件,项目经理决定必须外包部分项目工作。为确保满足需求和时间线,需要下列哪一项输入?

A.合格卖方清单和范围

B.进度和范围

C-成本估算和绩效

D.成本估算和进度

PMP答案解析:规划采购管理的输入。

PMP参考答案:B

阅读本文的人还阅读了:
pmp证书挂靠一年多少钱?
pmp证书含金量如何?
PMP报名资格是什么?
pmp报名官网是什么?
pmp考试报名费?
pmp考试是英文的吗?
pmp考试多少分通过?


PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库