PMP考试每天一练-2020年PMP考试试题45
PMP考试试题一: A project manager obtains seller responses, as well as selects a seller to provide one of the project’s key components. The project manager completed which of the following processes? A.Control procurements B.Direct and manage project work C.Plan procurement management D.Conduct procurements 项目经理获得供应商响应,并选择了一名供应商提供项目的其中一个关键组成部分。项目经理完成的是下列哪一个过程? A.控制采购 B.指导和管理项目工作 C.规划采购管理 D.进行采购 PMP答案解析:D的英文Conduct procurements是实施采购。实施采购是获得卖方应答并选择卖方。 PMP参考答案:D PMP考试试题二 To complete a product and release it as planned, the project budget must be increased significantly. The project sponsor asks for a cost estimate.Which method for cost estimation should be used? A. Earned value (EV) B. Reserve analysis C. Program evaluation and review technique (PERT) D. Parametric estimating 为完成一项产品并按计划发布,必须增加大量项目预算。项目发起人要求执行成本估算。应使用哪种成本估算方法? A.净值(EV) B.储备分析 C.计划评审技术(PERT) D.参数估算 PMP答案解析:为应对成本的不确定性,成本估算中可以包括应急储备。随着项目信息越来越明确,可以动用、减少或取消应急储备。 PMP参考答案:B |