PMP考试每天一练-2020年PMP考试试题42
PMP考试试题一: The project is over budget, but several opportunities to reduce the project’s cost were previously identified. The project manager would like to exploit these opportunities.Which of the following should the project manger review first? A.risk register B.cost management plan C.change control system D.risk management plan 项目超出预算,但是之前已经确定出多个减低成本的机会。项目经理希望利用这些机会。项目经理应首先审查下列哪一项? A.风险登记册 B.成本管理机会 C.变更控制系统 D.风险管理计划 PMP答案解析:“机会”是积极的风险,风险登记册中有风险清单和潜在的应对措施。 PMP参考答案:A PMP考试试题二 During testing of a new software program, the test team logs the number of defects found each week. The project manager reviews the data to determine if the number of defects is within the acceptable limits.What tool does the project manager use? A. Control chart B. Cause and effect diagram C. Pareto chart D. Histogram 在测试一个新的软件项目集期间,测试团队记录每周发现的缺陷数量。项目经理审查数据确定缺陷数量是否处于可接受限值之内。项目经理使用的是什么工具? A.控制图 B.因果图 C.帕累托图 D.直方图 PMP答案解析:PMBOK:控制图,可用来监测成本与进度偏差、产量、范围变更频率或其他管理工作成果,以便帮助确定项目管理过程是否受控。 PMP参考答案:A |