PMP考试每天一练-2020年PMP考试试题38

转载者:PMP团购网      发布时间:2020/3/20        点击: 1633

PMP考试试题一:

The steering committee wants to replace project manager A. project manager A’s company decides to keep project manager A on the project as a backup and assigns project manager B as the project lead.Which of the following processes was used to address this issue?

A.Monitor and control project work

B.Manage project team

C.Perform integrated change control

D.Manage stakeholder engagement

指导委员会希望更换项目经理A。项目经理A 的公司决定保留项目经理A在项目上作为备份,同事分配项目经理B作为项目主管。下列那一项过程被用来解决这个问题?

A.监控项目工作

B.管理项目团队

C.实施整体变更控制

D.管理干系人参与程度

PMP答案解析:涉及项目治理和高层决策,是管理干系人的范畴。

PMP参考答案:D

PMP考试试题二

Stakeholders ask a project manager about a project's financial status. The current cost performance index (CPI) is 0.8 and the schedule performance index (SPI) is 1.2.What should the project manager use to determine the project's performance status?

A. Trend analysis

B. Completed actions documentation

C. Project budget status reporting

D. Performance index calculations

干系人向项目经理询问一个项目的财务状态。目前,成本绩效指数(CPI)为0.8,进度绩效指数(SPI) 为1.2。项目经理应使用哪一项来确定项目的绩效状态?

A.趋势分析

B.已完成工作文档

C.预算状态报告

D.绩效指数计算

PMP答案解析:CPI=0.8,SPI=1.2,成本超支、进度提前。通过绩效指数确定项目的绩效状态。

PMP参考答案:D

阅读本文的人还阅读了:
pmbok第六版 pdf下载
pmbok第六版中文版下载
pmbok第六版 pdf下载百度云
pmbok第6版pdf百度网盘
pmbok第六版电子版
pmp考试多少分通过?
pmp考试通过率?
什么是pmp认证?
pmp认证的级别?

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库