PMP考试每天一练-2020年PMP考试试题37

转载者:PMP团购网      发布时间:2020/3/18        点击: 1680

PMP考试试题一:

A company’s system is being implemented. After an analysis of incidents registered by the help desk, the project manager builds a histogram with these results.This activity and its frequency should be described in which of the following?

A.Risk response plan

B.Quality management plan

C.Quality audit plan

D.Schedule management plan

一家公司的系统正在实施过程中。在对服务台登记的事件进行分析之后,项目经理利用这些结果制作了一份直方图。这项活动及其频率应描述为下列哪一项?

A.风险应对计划

B.质量管理计划

C.质量审计计划

D.进度管理计划

PMP答案解析:This activity and its frequency should be described in which of the following?可以翻译为:这项活动及其频率应描述在下列哪一项中?直方图是规划质量管理过程的工具,质量管理计划是规划质量管理的输出。只有B最合适。

PMP参考答案:B

PMP考试试题二

After noticing a conflict within the team, the project manager attempts to resolve the conflict by emphasizing the areas on which the team agrees and de-emphasizing the areas on which the team disagrees, this is an example of which of the following conflict resolution techniques

A, Compromise/Reconcile

B. Smooth/Accommodate

C. Collaborate/Problem Solve

D. Withdraw/Avoid

在得知团队中发生冲突之后,项目经理尝试通过强调团队达成共识的方面,而不强调未达成共识的方面来解决冲突。这属于以下哪一种冲突解决技术的范例?

A妥协/调节

B.缓解/包容

C.合作/解决问题

D.撤退/回避

PMP答案解析:求同存异是缓解/包容。

PMP参考答案:B

阅读本文的人还阅读了:
pmp考试是英文的吗?
pmp考试多少分通过?
pmp认证考试是什么?
pmp认证考试怎么报名?
pmp培训远程还是面授好?
pmp培训远程还是面授,怎么选?
PMP远程对比面授有哪些优势?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库