PMP考试试题一:

As the project nears completion, the customer voices concerns with the quality of the product delivered. What method will identify the extent of the quality issues?

A.Six sigma

B.Risk audit

C.Statistical sampling

D.Expert judgment

随着项目临近完工,客户表达了对于已交付产品质量的担忧。用什么方法将识别质量问题的范围?

A.六西格玛

B.风险审计

C.统计抽样

D.专家判断

PMP答案解析:the extent of the quality issues,质量问题的范围、质量问题的程度。控制质量可以识别质量问题的程度,统计抽样是控制质量的工具。

PMP参考答案:C

PMP考试试题二

During a company’s relocation to a new data center, a project team member discovers that the new data center’s power supply will not be sufficient. To support forecasted growth over the next three years, additional resources costing US$480,000 will be required. As the project manager had previously identified this as a risk, what tool should have been used to determine if the contingency budget would adequately cover this costs?

A. Status meeting

B. Reserve analysis

C. Risk reassessment

D.Technical performance measurement

在公司迁址到一个新数据中心期间,一名项目团队成员发现新数据中心的电源不足。为了支持在未来三年内的预测增长,将需要US$48万的额外资源。由于项目经理之前已将此识别为一个风险,应使用什么工具来确定应急储备足以涵盖成本?

A.状态会议

B.储备分析

C.风险再评估

D.技术绩效测量

PMP答案解析:储备分析是在项目的任何时候,比较剩余应急储备与剩余风险量,从而确定剩余储备是否仍然合理。

PMP参考答案:B

阅读本文的人还阅读了:
2020年PMP考试费用?
2020年PMP考试费是多少?
PMP考试费用及缴费方式是什么?
PMP培训哪个好?
PMP需要培训吗?
不参加PMP培训可以吗?
PMP培训多少钱?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库