PMP考试每天一练-2020年PMP考试练习题1
PMP考试练习题一: A risk in the risk register is realized late in the project. What would be the most effective response to the situation? A. Use the management reserve. B. Perform a quantitative risk analysis. C. Perform a qualitative risk analysis. D. Use the contingency reserve. 在风险登记册中的一个风险在项目后期发生。应对这种情况的最有效措施是什么? A.使用管理储备。 B.执行定量风险分析。 C.执行定性风险分析 D.使用应急储备。 PMP答案解析:对于已知风险发生使用应急储备。 PMP参考答案:D PMP考试练习题二 A project team member's behavior is disruptive and does not comply with the company's standards. The project manager speaks with the team member, but there is no improvement ill their behavior.What should the project manager do next? A. Request that the functional manager reassign the team member B. Escalate the issue to the project sponsor C. Organize a project team meeting to reinforce the company's standards D. Request support from the human resource department 项目团队成员的行为具有破坏性,且与公司标准不符。项目经理与团队成员谈话,但是他们的行为并无任何改进。 A.请求职能经理重新分配团队成员 B.将该问题上报给项目发起人 C.安排项目团队会议,强调公司标准 D.请求人力资源部门的支持 PMP答案解析:进行正式口头沟通。 PMP参考答案:C |