PMP考试每天一练-2019年PMP考试试题189
PMP考试试题一: Task A has a cost estimate of US$1,000 and scheduled completion date of December 30th, with a total duration of 10 days. The project manager reviews the task’s progress on December 27th, and it is 50% complete. The resource assigned to task A has spent US$500 to date.By adding a resource, the project manager is using which of the following? A.Budgeting B.Crashing C.Fast tracking D.Damage controlling 任务A的成本估算为1000美元,计划完成日期是12月30日,总工期为10天。项目经理在12月27日查看任务进度发现,任务完成50%。到目前为止分配给任务A的资源已经花了500美元。通过增加一名资源,项目经理使用的是下列哪一项? A.制定预算 B.赶工 C.快速跟进 D.损害控制 PMP答案解析:通过增加资源来压缩工期 PMP参考答案:B PMP考试试题二 Project team members are participating in a work stoppage in solidarity with members of their trade union. Due to safety concerns, this action causes a three-day project delay. How should the project manager address this? A. Change the project schedule. B. Negotiate with the trade union C. Arrange a brainstorming session. D. Issue a change request. 项目团队成员正在参与停工,声援他们的工会成员。出于安全考虑,这项行动导致项目延期三天。项目经理应该如何解决这个问题? A.变更项目进度计划。 B.与工会协商。 C.安排一次头脑风暴会议。 D.签发变更请求。 PMP答案解析:通过变更请求来处理进度计划的变更。 PMP参考答案:D |