Due to an increased rate of natural disasters along a flood plain, a warehouse director wants to initiate a project to review and update the disaster management plan. Which of the following should the project manager use to identify the project risks?

A. Risk probability and impact assessment

B. Brainstorming

C. Risk rating and ranking

D, Flowchart

由于洪灾,平原沿线发生自然灾害的频率增加,仓库主任希望启动一个项目,审查和更新灾难管理计划。项目经理应该使用下列哪一项来识别项目风险?

A.风险概率与影响评估

B.头脑风暴

C.风险评级和排序

D.流程图

PMP答案解析:头脑风暴是识别风险工具的信息收集技术。

PMP参考答案:B

PMP考试试题二

During a project's initiation, a new project manager is hired. The previous project manager identified the project stakeholders.In which of the following documents will the new project manager find information regarding stakeholder relationships?

A. Stakeholder communication requirements

B. Project organization chart

C. Stakeholder management plan

D. Project charter

在项目启动阶段,聘用了一名新项目经理。前任项目经理已经识别了项目干系人。新项目经理可以在下列哪一份文件中找到干系人关系方面的信息?

A.干系人沟通需求

B.项目组织图

C.干系人管理计划

D.项目章程

PMP答案解析:启动阶段要查看干系人关系方面的信息,可以查看干系人管理计划。

PMP参考答案:C

阅读本文的人还阅读了:
PMP证书是什么证?
PMP证书好考吗?
参加PMP考试需要多少费用?
2020年PMP考试时间及报名时间
PMP考试费用为什么这么贵?
PMP培训费和考试费是多少?
PMP培训机构哪家强?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库