PMP考试试题一:

The project manager is informed by the company’s internal auditor that the project documentation must be reviewed at the next quality audit. What is the purpose of this audit?

A.Verify that the production quality meets customer expectations

B.Check that the company’s quality process is followed

C.Ensure the company’s processes align with ISO 9001

D.Meet process improvement recommendations

公司内部审计员通知项目经理必须在下一次质量审计时审查项目文档。该审计的目的是什么?

A.验证产品质量是否符合客户期望

B.检测是否遵循公司的质量过程

C.确保公司的过程符合ISO9001

D.满足过程改进建议

PMP答案解析:质量审计是用来确定项目活动是否遵循了组织和项目的政策、过程与程序。

PMP参考答案:B

PMP考试试题二

During project initiation, a key stakeholder claims the project is no longer viable. What should the project manager do to evaluate the project’s viability?

A. Refer the stakeholder to the project sponsor.

B. Delay reassessment until project funding is exhausted at the end of initiation.

C. Check alignment with the business case and present to sponsor and key stakeholders.

D. Start the project closure process immediately.

在项目启动期间,一名关键干系人声称项目不再可行。为评估项目的可行性,项目经理应该怎么做?

A.将该干系人推荐给项目发起人。

B.拖延项目再评估,直至项目资金在启动阶段结束时用完。

C.检查是否与商业论证保持一致,并提交给项目发起人和关键干系人。

D.立即开始项目收尾过程。

PMP答案解析:再进行商业论证,评估可行性。

PMP参考答案:C

阅读本文的人还阅读了:
PMP通过率怎么样?
PMP考试通过率高不高?
PMP认证的含金量如何?
pmp挂靠一年多少钱?
PMP培训哪个好?
PMP需要培训吗?


网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库