PMP考试每天一练-2019年PMP考试试题182
PMP考试试题一: A project manager is assigned a project with a limited schedule, and realizes that the deadline is at the end of the year when most team members take their vacations. In which document would the project manager expect to find this high-level risk? A.Project charter B.Issue log C.Work breakdown structure D.Organizational process assets 项目经理被任命管理一个工期有限的项目,并意识到项目期限处于大部分团队成员都在休假的年底。项目经理可在哪一份文件中找到该高风险? A.项目章程 B.问题日志 C.工作分解结构 D.组织过程资产 PMP答案解析:项目章程中有高层级风险(high-level risk) PMP参考答案:A PMP考试试题二 An innovative project has poorly defined product requirements. During the kick-off meeting, on what should the project manager focus? A. Conducting a requirements analysis with the stakeholders B. Agreeing on the work deliverables, schedule, resources, and costs C. Validating the project charter with the stakeholders D. Ensuring everyone is aligned with the project requirements 一个创新项目的产品需求定义很差。在项目启动大会上,项目经理应该关注哪一点? A.与项目干系人开展需求分析 B.约定工作可交付成果、进度计划、资源和成本 C.与项目干系人一起核实项目章程 D.确保每个人与项目需求保持一致 PMP答案解析:通过核实项目章程与干系人进行高层级共识。 PMP参考答案:C |