PMP考试每天一练-2019年PMP考试试题179
PMP考试试题一: The procurement department collects and delivers vendor quotes to the project manager. The project sponsor asks for the project team's recommendations regarding vendor selection. What should the project manager do? A. Review the Quotes and select the quote based on the best price only. B. Conduct a project team meeting to obtain a recommendation C. Review the quotes and select a vendor that previously worked with the company D. Recommend a vendor based on a match with the selection criteria 采购部门收集供应商报价,并将其提交给项目经理。项目发起人征求项目团队对于供应商选择的建议。项目经理应该怎么做? A.审查报价,并仅根据最佳价格选择报价 B.召开项目团队会议,获得建议 C.审查报价并选择之前与公司合作过的供应商 D.根据是否与选择标准匹配推荐供应商 PMP答案解析:根据供方选择标准来选择供应商。 PMP参考答案:D PMP考试试题二 During project execution, team members are concerned about the effectiveness of the development process. The project manager should follow the procedures in which of the following? A.Quality management plan B.Schedule management plan C.Process control plan D.Requirements management plan 项目执行期间,团队成员担心开发过程的效率。项目经理应遵循下列哪一项程序? A.质量管理计划 B.进度管理计划 C.过程控制计划 D.需求管理计划 PMP答案解析:PMBOK原话:实施质量保证过程也为持续过程改进创造条件。持续过程改进是指不断地改进所有过程的质量。通过持续过程改进,可以减少浪费,消除非增值活动,使各过程在更高的效率与效果水平上运行。 PMP参考答案:A |