PMP考试每天一练-2019年PMP考试试题178
PMP考试试题一: During a project meeting, a team member identifies and submits a risk to the project manager. After an evaluation of the risk, the project team determines the impact, probability, and a risk response.Before performing these activities, what process must be completed? A.Plan risk management B.Identify risks C.Perform quantitative risk analysis D.Plan risk response 在项目会议上,一名团队成员识别到一个风险,并将其提交给项目经理。在评估完风险后,项目团队确定了影响、发生概率和风险应对措施。执行这些活动之前,必须完成那个过程? A.制定风险管理计划 B.识别风险 C.实施定量风险分析 D.制定风险应对计划 PMP答案解析:在“识别风险、风险定性分析、规划风险应对”之前,需要做的是规划风险管理。 PMP参考答案:A PMP考试试题二 A project relies on a specialized tool to keep track of several critical path activities. The specialized tool fails, but is quicklyreplaced by a backup tool, What describes this situation? A. Exploiting an opportunity to avoid risk B. Effectively using risk avoidance C. Deploying a successful risk mitigation strategy D. Managing risk closure through risk prevention 一个项目依靠专业工具来跟踪几个关键路径上的活动。专业工具发生故障,但很快被一个备份工具所取代。下列哪一项能够描述这个情况? A.开拓机会,回避风险 B.有效利用风险回避措施 C.部署一个成功的风险减轻策略 D.通过风险预防管理风险关闭 PMP答案解析:是一个有效的风险减轻措施。 PMP参考答案:C |