PMP考试每天一练-2019年PMP考试试题177

转载者:PMP团购网      发布时间:2019/12/4        点击: 1817

PMP考试试题一:

As a result of the quality control process, a change request is generated and approved by the change control board.What should the project manager do next?

A.Arrange the implementation of the approved change

B.Evaluate the change request with change control board

C.Evaluate the risk if not to implement the change

D.Perform root cause analysis to determine the cause of the change

作为控制质量过程的结果,产生变更请求,并由变更控制委员会批准。项目经理下一步该怎么做?

A.安排批准变更的实施

B.与变更控制委员会一起评估变更请求

C.评估如果不实施变更的风险

D.执行根本原因分析确定变更的缘由

PMP答案解析:变更请求获得批准后,下一步是更新项目管理计划、实施变更。

PMP参考答案:A

PMP考试试题二

A company completes an office building relocation project. Although the new office building is superior to the old building, many employees are not satisfied, because the new building is farther from their homes.How should the project manager address this situation?

A.Create a risk register, including the probability and impacts of the risk

B.Mitigate the impacts by following the risk response plan

C.Contact the functional managers and update the risk register

D.Transfer this risk to the human resources department, suggesting a better salary structure

公司完成一个办公楼迁移项目,虽然新办公楼优于旧办公楼,但因为新办公楼离许多员工的家较远,许多员工并不满意。项目经理应该如何解决这种情况?

A.创建风险登记册,包括风险概率和影响

B.通过遵循风险应对计划减轻影响

C.联系职能经理并更新风险登记册

D.将这个风险转移给人力资源部门,建议更好的工资结构

PMP答案解析:已识别的风险发生,执行应对措施。

PMP参考答案:B

阅读本文的人还阅读了:
2020年PMP考试时间及报名时间
PMP考试费用为什么这么贵?
2020年PMP考试时间?
2020年PMP考试费用?
广州PMP考试地点
PMP考试报名资格怎么审查?
PMP认证培训怎么选机构?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库