PMP考试每天一练-2019年PMP考试试题176
PMP考试试题一: Since the quality of the completed project is important to the end user, the project manager outlines how to achieve a quality project to the end user. The following? A.Quality metrics B.Lessons learned from a similar project C.Quality management plan D.Communications management plan 由于已完成项目的质量对最终用户非常重要,项目经理简要描述如何向最终用户完成高质量项目。项目经理应该分享下列哪一项? A.质量测试指标 B.类似项目的经验教训 C.质量管理计划 D.沟通管理计划 PMP答案解析:质量管理计划描述将如何实施组织的质量政策,以及项目管理团队准备如何达到项目的质量要求。 PMP参考答案:C PMP考试试题二 One project activity has a free float of two days. What statement can be made about the project? A. The total float of the project in two days. B. The project's subsequent activities can be rescheduled if the activity is delayed by two days. C. The activity can be delayed by two days without impacting subsequent activities start dates. D. The activity may be on the critical path. 一个项目活动有两天的自由浮动时间。下列哪个说法适合这个项目? A.项目的总浮动时间为两天 B.如果该活动延期两天,可以对项目的后续活动重新安排进度计划 C.该活动可以延迟两天,而不会影响后续活动的开始日期 D.该活动可能在关键路径上 PMP答案解析:自由浮动时间为自由时差,说明活动推迟2天而不会影响紧后活动的最早开始日期。 PMP参考答案:C |