PMP考试每天一练-2019年PMP考试试题171
PMP考试试题一: Which of the following organizational types is the most efficient for executing several small projects that require different technical expertise? A.Weak matrix B.Projectized C.Balanced matrix D.composite 下列那一项是执行需要不同技术知识的多个小项目最有效的组织类型? A.弱矩阵型 B.项目型 C.平衡矩阵型 D.复合型 PMP答案解析:既要不同技术知识、又要执行多个小项目,复合型比较合适。 PMP参考答案:D PMP考试试题二 An internal auditor develops a checklist to ensure project closure is complete. Which of the following activities should be included in the checklist? A. Archive project data B. Conduct variance analysis C. Obtain customer feedback D. Update the project schedule 一位内部审计员制定了一份核对表,确保项目收尾完成。核对表中应包含下列哪一项活动? A.项目数据归档 B.执行偏差分析 C.获得客户反馈 D.更新项目进度 PMP答案解析:行政收尾程序中一定要做的只有A,文件归档。 PMP参考答案:A |