PMP考试每天一练-2019年PMP考试试题169
PMP考试试题一: A project manager meets with two team members who maintain opposing viewpoints. In the meeting, the project manager emphasizes areas of agreement and plays down differences Which conflict management technique is the project manager practicing? A.Confront B.Smooth C.Force D.collaborate 项目经理与两名持相反观点的团队成员开会。会议中,项目经理强调一致而非差异。项目经理采用的是那种冲突管理技术 A.面对 B.缓解 C.强迫 D.合作 PMP答案解析:强调一致而非差异,这是求同存异。 PMP参考答案:B PMP考试试题二 Midway through the project, the project manger must determine if the planned budget will be sufficient to complete the project. Which of the following should the project manager calculation and then compare with the original budget A.Estimate to complete B.Estimate at completion C.Earned value D.Budget at completion 在项目中途,项目经理必须决定计划预算是否足以完成该项目。项目经理应该计算下列哪一项值再与原始预算对比? A.完工尚需估算 B.完工估算 C.挣值 D.完工预算 PMP答案解析:计划预算是BAC,需要用EAC与之对比。 PMP参考答案:B |