PMP考试每天一练-2019年PMP考试试题168

转载者:PMP团购网      发布时间:2019/11/15        点击: 1526

PMP考试试题一:

A complex part for a project needs to be constructed. The project manager decides to create a bench-scale model to manage the risks associated with this task. What risk strategy is the project manager using?

A. Avoid

B. Accept

C. Mitigate

D. Transfer

需要建造一个项目的复杂部分。项目经理决定创建一个实验室规模的模型来管理与这项任务有关的风险。项目经理采用了何种风险策略?

A.回避

B.接受

C.减轻

D.转移

PMP答案解析:题意描述可以理解为原型法,属于减轻措施。

PMP参考答案:C

PMP考试试题二

An organization is downsized but the same number of projects continues to be implemented. After learning about the downsizing, the customer expresses concerns to the project manager about potential issues with the quality of the products.What should the project manger do?

A. Escalate the concerns to organizational leadership

B. Recommend project closure, because quality products may not be delivered

C. Continue with the project even though it may require fast tracking and crashing

D. Inform the customer about the project team's qualifications.

一家组织裁员,但是还要继续执行相同数量的项目。得知裁员消息后,客户向项目经理表达了有关产品质量潜在问题的担忧。项目经理应该怎么做?

A.将问题上报给组织领导层

B.建议项目收尾,因为可能不能交付高质量的产品

C.继续项目,即使可能需要快速跟进和赶工

D.通知客户有关项目团队的合格证明情况

PMP答案解析:超出PM范围权限,应该上报公司管理层。

PMP参考答案:A

阅读本文的人还阅读了:
2020年PMP考试费用?
2020年PMP考试日期是什么?
pmp认证培训费用多少?
pmp项目管理师是什么?
pmp证书是什么?


网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库