PMP考试试题一:

A junior project team member requests approval of a purchase order an item listed in the work breakdown structure (WBS). After reviewing the project budget, the project manager realizes that the item on the purchase order is not listed in the project budget.What should be the reason for this issue?

A. The scope baseline was pot used as an input during the estimate costs process

B. Expert judgment was not used during the estimate cost process

C. Procurement planning was not used during the estimate process

D. The bottom-up estimating method was used during estimate costs process

初级项目团队成员请求批准工作分解结构(WBS)中所列某项物品的采购订单。审查项目预算后,项目经理发现采购订单上的物品未列入项目预算。造成这个问题的原因是什么?

A.在估算成本过程中未将范围基准作为一项输入

B.在估算成本过程中未使用专家判断

C.在估算成本过程中未使用采购规划

D.在估算成本过程中使用了自下而上估算法

PMP答案解析:估算成本时没有参考范围基准作为输入。

PMP参考答案:A

PMP考试试题二

1The project’s budget is US$750,000. At day 42, 40% of the project is completed, at a cost of US$500,000. After the project manager reports the cost performance index, the customer refuses to add more funds to the project.To complete the project on time and on budget, the project’s to-complete performance index must by which of the following?

A.0.6

B.0.8

C.1.4

D.1.8

项目预算为750,000没有。在第42天时,项目已完成40%,成本为500,000美元。在项目经理报告成本绩效指数后,客户拒绝为项目增加更多资金。若要按时按预算完成项目,项目的完工尚需绩效指数必须为下列哪一项?

A.0.6

B.0.8

C.1.4

D.1.8

PMP答案解析:D

PMP参考答案:TCPI=(BAC-EV)/(BAC-AC)=(750000-0.4*750000)/(750000-500000)=1.8

阅读本文的人还阅读了:
PMP认证费用多少?
PMP认证多少钱?
英语不好可以考PMP吗?
PMP证书与学历挂钩吗?
PMP退考费多少?
PMP认证抽审流程是什么?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库