PMP考试每天一练-2019年PMP考试试题156
PMP考试试题一: Referring to the control chart, what can be concluded about this process? A.In control, despite six measurements after April diverge from the mean B.Out of control, due to the fluctuations in February and April C.Out of control, because six measurements after April diverge from the mean D.In control, because one measurements was more than three standard deviations below mean 参考控制图,可以对这个过程得出什么结论? A.在控制中,即使四月份后六个测量值偏离平均线 B.失去控制,因为而鱼粉和四月份的波动 C.失去控制,因为四月份后六个测量值偏离平均线 D.在控制中,因为一个测量值超过平均线下方的三个标准偏差 PMP答案解析:根据七点规则,四月份后只有六个点在均值的同一侧。 PMP参考答案:A PMP考试试题二 During a project’s execution, the program manager advises the project manager that the project will be cancelled. What should the project manager do next? A.Reassign the resources to other projects B.Meet with the project sponsor and the program manager C.Continue the phase to completion D.Create a change request for the delivery manager 在项目执行期间,项目集经理通知项目经理项目将被取消。项目经理下一步该怎么做? A.向其他项目重新分配资源 B.与项目发起人和项目集经理开会 C.继续阶段完成 D.向交付经理创建一份变更请求 PMP答案解析:项目经理接到通知项目将被取消,应该进行项目收尾,做好经验教训总结。 PMP参考答案:B |