During a construction project, an identified risk occurs. After the project manager implements the mitigation plan for this risk, additional actions are required.To identify the next steps, what document should the project manager review?

A.Risk response plan

B.Risk register

C.Risk workaround

D.Risk management plan

在一个施工项目期间,发生了一项已识别的风险。项目经理实施了风险减轻计划后,要求采用额外措施。若要确定下一步措施,项目经理应该查看那份文件?

A.风险应对计划

B.风险登记册

C.风险权变措施

D.风险管理计划

PMP答案解析:人员配备管理计划描述如何满足项目对人力资源的需求。

PMP参考答案:C

PMP考试试题二

Five projects are planned to be completed within a year under the authority of one sponsor, A functional manager, who owns the project resources, begins to implement all five projects according to the sponsor's request. However, the project manager believes all five projects cannot be completed due to limited resources and budget.What should the project manager do during the initiating phase to document this concern?

A. Perform cost and time analysis to determine if five projects can be completed within the year.

B. Follow the sponsor's request

C. Withdraw from the project

D. Document the concern as a high-level risk and a constraint for each of the five projects.

五个项目在一名发起人的授权之下,计划在一年内完成。一名拥有项目资源的职能经理开始按照发起人的要求执行所有五个项目。但是,项目经理却认为由于资源和预算有限无法完成所有五个项目。项目经理应该在启动阶段怎么做来记录该问题?

A.执行成本和时间分析,确定五个项目是否能够在一年内完成

B.遵循发起人的要求

C.退出该项目

D.将该问题记录为所有五个项目共有的高级别风险和制约因素

PMP答案解析:在启动阶段识别高层次风险和项目制约因素。

PMP参考答案:D

阅读本文的人还阅读了:
2020年PMP考试费是多少?
2020年PMP考试时间和报考条件是什么?
PMP考试费用及缴费方式是什么?
pmp项目管理师是什么?
pmp证书是什么?
PMP证书有用吗?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库