PMP考试试题一:

A project manager's construction project is on time, on scope, and within budget. The project manager learns that a favorable weather forecast will allow for the implementation of critical path activities earner man expected,What should the project manager do first?

A. Revise the schedule.

B. Initiate perform integrated change control process.

C. Check risk register.

D. Follow the planned schedule.

项目经理的施工项目符合时间、范围以及预算。项目经理了解到有利的天气预报将允许比预期提前执行关键路径上的活动。项目经理首先应该做什么?

A.修订进度计划。

B.开始执行整体变更控制过程。

C.检查风险登记册。

D.遵循计划的进度计划。

PMP答案解析:题意描述属于积极风险,查询风险登记册中关于此项积极风险的应对措施。

PMP参考答案:C

PMP考试试题二

During a construction project, an identified risk occurs. After the project manager implements the mitigation plan for this risk, additional actions are required.To identify the next steps, what document should the project manager review?

A.Risk response plan

B.Risk register

C.Risk workaround

D.Risk management plan

在一个施工项目期间,发生了一项已识别的风险。项目经理实施了风险减轻计划后,要求采用额外措施。若要确定下一步措施,项目经理应该查看那份文件?

A.风险应对计划

B.风险登记册

C.风险权变措施

D.风险管理计划

PMP答案解析:对于已识别的风险,PM实施了风险减轻计划后,可能效果不好、或者产生了次生风险、或者是其他原因要求采用额外的措施,应该查看风险登记册,里面有:商定的应对策略及其
具体行动、应急计划和触发因素等等。 选项C风险权变措施,这个是针对未知风险发生而随机应变临时制定的,无法事先查看。

PMP参考答案:B

阅读本文的人还阅读了:
PMP认证费用多少?
PMP认证多少钱?
PMP考试难吗?
PMP考试报名条件是什么?
PMP认证报名条件是什么?
不参加PMP培训可以考PMP吗?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库