PMP考试试题一:

A key stakeholder asks the project manager to quantify the project risks. Which of the following documents should the project manager use to provide the requested information?

A.Cost management plan and schedule management plan

B.Schedule management plan and human resource management plan

C.Human resource management plan and cost management plan

D.Scope baseline and cost management plan

一名关键干系人要求项目经理量化项目风险。项目经理应使用下列那一份文件来提供所请求的信息?

A.成本管理计划和进度管理计划

B.进度管理计划和人力资源管理计划

C.人力资源管理计划和成本管理计划

D.范围基准和成本管理计划

PMP答案解析:定量风险分析的输入。

PMP参考答案:A

PMP考试试题二

A project manager terminates a contract for the design of a two-part report, because the first part did not meet the criteria in the statement of work. After a new request for proposal is distributed, the selection committee awards a new contract to another designer.During the contract closure process, the project manager should do which of the following?

A.Review the procurement processes

B.Update the project management plan

C.Include the terminated contract in the lessons learned documentation

D.Prepare a completion certificate for the terminated contract

项目经理终止一份包含两部分设计报告的合同,因为第一部分不能满足工作说明书中的标准。在分发新的请求建议书后,选择委员会将新合同授予另外一个设计师。在合同收尾过程中,项目经理应进行下列哪一项?

A.审查采购过程

B.更新项目管理计划

C.将终止合同包含进经验教训文档中

D.为终止的合同准备一份完工证明

PMP答案解析:将终止合同包含进经验教训文档中。

PMP参考答案:C

阅读本文的人还阅读了:
PMP考试有什么科目?
PMP考试三个月来得及吗?
广州PMP考试地点
2020年PMP考试日期是什么?
2020年PMP考试费是多少?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库