PMP考试试题一:

The project manager identified multiple problems which have negative impact on a strategic project goal. What should the project manage do next?

A.Prioritize the problems according to the influence on project objectives

B.Hold a special project meeting to assign the issue to team members

C.Get the approval of project sponsor to change the project objectives

D.Use project contingence reserve to assign additional resource to solve the problem

项目经理识别出可能对一个战略项目目标产生负面影响的多个问题。项目经理下一步该怎么做?

A.确保根据对项目目标的影响对每个问题赋予优先级

B.召开一次特别项目会议,将问题委派给团队成员

C.获得项目发起人的批准,变更项目目标

D.使用项目应急储备,分配额外的资源解决问题

PMP答案解析:PM识别出可能对目标产生影响的多个问题,可对多个问题排列优先级,优先关注重要问题。

PMP参考答案:A

PMP考试试题二

A truck carrying critical products for a project is in a traffic accident and the products are destroyed, The project manager should refer to which of the following for a contingency plan?

A. Risk reassessment

B. Quantitative risk analysis

C. Risk register

D. Contingency reserves

一辆运送项目关键产品的卡车发生交通事故,产品被销毁。项目经理应参阅下列哪一份文件获得应急计划?

A风险再评估

B.定量风险分析

C.风险登记册

D.应急储备

PMP答案解析:四个答案中,最好的选项为 C。应急计划是事先确定好的,在一定特殊条件可以启动的计划。

PMP参考答案:C

阅读本文的人还阅读了:
PMP报名时间
PMP考试费用
最新PMP考试时间
2020年PMP考试时间?
2020年PMP考试费用?
2020年PMP考试日期是什么?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库