PMP考试试题一:

A project manager asks team members to submit project documents by a specific date. Some team members do not submit their documents on time, claiming that it was unclear what documents were expected. What should the project manager do?

A. Hold a project meeting to collect the completed project documents.

B. Ask the team members' supervisors to direct the team members to submit the documents.

C. Report the issue to the customer and ask them to change the due date.

D. Review the work breakdown structure (WBS) to clarify tasks for the team members.

项目经理要求团队成员在某个特定日期之前提交项目文件。有些团队成员未按时提交文件,声称对提交哪些文件不清楚。项目经理应该怎么做?

A.召开项目会议,收集已完成的项目文件。

B.让团队成员监督员指示团队成员提交文件。

C.将该问题报告给客户,并要求他们变更截止日期。

D.审查工作分解结构(WBS),为团队成员澄清任务。

PMP答案解析:四个选项中D为最优选项。

PMP参考答案:D

PMP考试试题二

During a project phase review, the project manager discovers that the project does not have the support of the project stakeholders. What is the level to ensure successful project completion?

A. Supportive

B. Unaware

C. Neutral

D. Leading

在项目阶段评审会上,项目经理发现项目未获得所有项目干系人的支持。确保成功完成项目所需的参与层次是什么?

A.支持

B.不知道

C.中立

D.领导

PMP答案解析:PMBOK:领导。知晓项目和潜在影响,积极致力于保证项目成功。

PMP参考答案:D

阅读本文的人还阅读了:
PMP报名流程
PMP报名时间
PMP考试费用
PMP证书在哪个行业比较有用
PMP的价值在哪?
PMP认证考试的报名条件?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库