PMP考试每天一练-2019年PMP考试试题136

转载者:PMP团购网      发布时间:2019/10/9        点击: 2116

PMP考试试题一:

A project manager generates information about internal and external parties who are involved in and affected by the project and its outcome. Which of the following contains information that the project manager should use for the parties involved?

A.Project communications management plan

B.Project charter

C.Project organizational chart

D.Project management plan

项目经理只做了将参与以及受到项目及其成果影响的内外各方信息。下列哪一项包含了项目经理应该用于参与各方的信息?

A.项目沟通管理计划

B.项目章程

C.项目组织图

D.项目管理计划

PMP答案解析:沟通管理计划中包含了干系人的沟通需求、需要沟通的信息等等。

PMP参考答案:A

PMP考试试题二

A project sponsor asks a project manager to validate that corporate quality standards are consistently being met. To complete this task, what sequence of activities should the project manager perform

A. Quality plan update and quality plan baseline update

B. Quality audit and quality assurance

C. Quality assurance and quality control

D. Quality checklist review and quality control

项目发起人要求项目经理核实,公司的质量标准始终得到满足。若要完成这个任务,项目经理应执行什么序列的活动?

A.质量计划更新和质量计划基准更新

B.质量审计和质量保证

C.质量保证和质量控制

D.质量核对表审查和质量控制

PMP答案解析:推荐C答案,B答案中质量保证包含质量审计,通过质量保证和质量控制来确保质量标准得到执行。

PMP参考答案:C

阅读本文的人还阅读了:
PMP考试是什么?
北京PMP培训团购
上海PMP培训团购
珠海PMP考试地点在哪里?
东莞PMP考试地点在哪里?
保定PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库