PMP考试试题一: After evaluating sellers' proposals, a project manager discovers a significant variance among their prices. This makes it difficult to compare the bids and make a decision. To determine the cause of the inconsistencies, what should the project manager do? A. Hold a bidder conference. B. Review the procurement statement of work (SOW). C. Report the differences to their manager. D. Review the project SOW. 评估卖方建议书后,项目经理发现他们的价格存在显著差异。这使得难以比较报价和做出决定。若要确定导致不一致的原因,项目经理应该怎么做? A.举行投标人会议。 B.审查采购工作说明书(SOW)。 C.将差异报告给他们的经理。 D.审查项目工作说明书。 PMP答案解析:采购SOW应该详细描述拟采购的产品、服务或成果,以便潜在的卖方确定他们是否有能力提供这些产品、服务或成果;如果出现明显的报价差异,需要审查是否 SOW的描述不准确。 PMP参考答案:B PMP考试试题二 A project sponsor asks a project team to execute a project's scope in a single phase. Which of the following should be presented to the project sponsor so that a multi-phased approach can be Used? A. Stakeholder analysis B. Requirements management plan C. High-level risks D. Flowchart 项目发起人要求项目团队在一个单独阶段执行项目范围。应向项目发起人提交下列哪一项才能使用多阶段方法? A.干系人分析 B.需求管理计划 C.高层次风险 D.流程图 PMP答案解析:阶段与阶段间的关系对如何管理需求有很大影响。项目经理为项目选择最有效的阶段间关系,并将它记录在需求管理计划中。 PMP参考答案:B |