PMP考试每天一练-2019年PMP考试练习题106

转载者:PMP团购网      发布时间:2019/8/30        点击: 1647

PMP考试练习题一:

A new project manager is assigned midway through a project. After conducting a project performance review, the project manager discovers that a supplier is unable to finish the work. At this stage, switching suppliers will carry considerable risk; however, not switching willresult in cost increases and schedule delays. What should the project manager do next?

A . Analyze the impact and formulate a plan.

B. Identify a new supplier as a replacement in case the issue recurs.

C. Help the supplier to resolve the issue and finish the work.

D. Ask management and the procurement department to resolve the issue.

项目经理接手了一个进展到一半的项目。在经过项目绩效审查后,项目经理发现其中一个供应商并不具备完成工作的能力,但项目已进展到一半,更换供应商会带来很大的风险。而不更换势必会造成成本增加以及工期延后。项目经理应该如何应对?

A.分析不同情况下所造成的影响,制定方案。

B.寻找新的供应商,在问题再次出现的时候直接替换。

C.协助供应商解决问题,辅助他们完成工作

D.交给采购部门去解决问题,并寻求管理层的帮助。

PMP答案解析:A答案包念了决策树与EMV值的含义,为四个选项中最优选项

PMP参考答案:A

PMP考试练习题二

During project execution, the project team is unsure about their responsibilities. Which of the following should the project manager have prepared?

项目执行期间,项目团队不确定各自的责任。项目经理应制定下列哪一项?

A.干系人分析

B.人员配备管理计划

C.项目管理计划

D.执行,负责,咨询和知情(RACI)矩阵

PMP答案解析:RACI矩阵是把人和事联系起来

PMP参考答案:D

阅读本文的人还阅读了:
工作年限不够可以考PMP吗?
PMP证书在哪个行业比较有用
PMP的价值在哪?
PMP认证考试的报名条件?
PMP报名流程
PMP报名时间
最新PMP考试时间
PMP考试地点

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库