PMP考试练习题一:

A quality audit identifies nonconformities for several deliverables on the critical path. Upon completion of corrective actions, the project manager needs to report the results to the change control board (CCB).What should the project manager do to validate conformity?

A. Complete quality checklists.

B. Inspect the changes.

C. Update the change 1Oq.

D. Complete a statistical sampling.

质量审计识别到关键路径上多个可交付成果的不一致之处。在完成纠正措施后,项目经理需要将结果报告给变更控制委员会(CCB)。若要核实一致性,项目经理应该怎么做?

A.完成质量核对表。

B.检查变更

C.更新变更日志。

D.完成统计抽样。

PMP答案解析:通过统计抽样来进行检测

PMP参考答案:D

PMP考试练习题二

A company’s executive team identifies a product that is underperforming and needs to be replaced. The project sponsor asks the project manager to initiate a new project to develop the replacement product.What should the project manager do first?

A. Submit the project charter to the project sponsor for approval.

B. Work with the project sponsor to identify the high level requirements for the replacement product.

C. Develop the project management plan.

D. Indentify the project stakeholders who will be involved in the development of the replacement product.

一家公司的执行团队识别到一项产品表现不佳,需要替换。项目发起人要求项目经理启动一项新项目,开发替换产品。项目经理首先应该做什么?

A.向项目发起人提交项目章程,用于批准。

B.与项目发起人合作,识别替换产品的髙层次需求。

C.制定项目管理计划

D.识别涉及替换产品并发工作的项目干系人

PMP答案解析:启动新项目,首先应该制定项目章程。

PMP参考答案:A

阅读本文的人还阅读了:
PMP考试内容是什么?
PMP考试有题库吗?
PMP考试报名费是多少?
PMP考试时间一年有几次?
PMP报名流程
PMP报名时间
最新PMP考试时间

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库