PMP考试每天一练-2019年PMP考试试题95
PMP考试试题一: Team members are complaining about the project leader's actions, which impacts overall project performance, the project manager discusses the issue with the project leader and team members, and suggests working through the discussion points to develop a solution. What conflict resolution technique does this describe? A. Collaborate/problem solve B. Withdraw/avoid C. Compromise/reconcile D. Force/direct 团队成员都在抱怨项目领导的行为,这会影响整个项目绩效。项目经理与项目领导和团队成员讨论这个问题,并建议通过讨论要点工作来制定解决方案。这描述的是什么冲突解决技术? A.合作/解决问题 B.撤退/回避 C.妥协/调解 D.强迫/命令 PMP答案解析:问题各方共同面对问题进行讨论来解决,属于冲突管理中合作解决问题的方式。 PMP参考答案:A PMP考试试题二 To report the quality test results on the deliverables, what should the project manager take to the stakeholders meeting? A.Work performance reports B.Updated quality management plan C.Process improvement plan D.Quality control measurements 为了报告可交付成果上的质量测量结果,项目经理应该携带什么材料参加干系人会议? A.工作绩效报告 B.更新的质量管理计划 C.过程改进计划 D.质量控制衡量 PMP答案解析:选项D就是质量控制测量结果,是对质量测量结果的记录。 PMP参考答案:D |