以下城市均已开通:
关闭
当前位置:PMP团购网 > PMP考试资料 > 正文

PMP考试每天一练-2019年PMP考试试题74

转载者:PMP团购网      发布时间:2019/6/21        点击: 2129

PMP考试试题一:

A project is delayed due to performance and procurement issues. The client is dissatisfied and requests a corrective action plan from the project manager. What should the project manager do?

A. Analyze and resolve the root causes of the delay.

B. Arrange a meeting with the chant to explain the reasons for the delay.

C. Fast track the schedule.

D. Review the procurement management plan.

项目由于绩效和采购问题延期。客户不满意,并要求项目经理提交纠正措施计划。项目经理应该怎么做?

A.分析和解决延期的根本原因。

B.与客户安排一次会议,说明延期的原因。

C.快速跟进进度计划。

D.审查采购管理计划。

PMP答案解析:首选分析原因,作为纠正措施制定的基础。

PMP参考答案:A

PMP考试试题二

While executing a schedule driven project, the schedule performance index becomes 0.5 The project manager applies fast tracking and schedule compression techniques without any success. What should the project manager do next?

A. Intiate the integrated change control process

B. Apply changes to the schedule baseline.

C. Ask the sponsor for additional resources.

D. Reduce the project scope.

在执行一个受进度驱动的项目时,进度绩效指数为0.8,项目经理应用了快速跟进和进度压缩技术,但不成功。项目经理下一步该怎么做?

A.启动整体变更控制过程。

B.对进度基准应用变更。

C.让发起人增加额外资源。

D.减少项目范围。

PMP答案解析:项目进度落后, PM采用了快速跟进和赶工的方法,但是效果并不好。所以接下来考虑变更进度基准或减少项目范围,这两者都属于整体变更控制

PMP参考答案:A

阅读本文的人还阅读了:
PMP的价值在哪?
PMP认证考试的报名条件?
PMP是什么?
长春PMP考试地点在哪里?
哈尔滨PMP考试地点在哪里?
重庆PMP考试地点在哪里?
珠海PMP考试地点在哪里?
东莞PMP考试地点在哪里?
保定PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库