PMP考试试题一: A project manager plans a multibillion-dollar project that will be funded by loans from international banks in one lump sum, What should the project manager consider to ensure an accurate budget? A. Exchange rates B. Discounting cash flows C. Time value of money D. Management reserve 项目经理为一个价值数十亿美元的项目制定计划,该项目将由来自国际银行的一次性支付贷款提供资金。若要确保预算准确,项目经理应该考虑到哪一点? A.汇率 B.贴现现金流 C.货币时间价值 D.管理储备 PMP答案解析:国际银行的资金来源,往往会涉及到汇率问题 PMP参考答案:A PMP考试试题二 An issue occurs when a vendor does not deliver a product on the agreed-upon date. The risk response plan requires the use of an alternate vendor that is more expensive but can deliver immediately.What should the project manager do next? A. Set up a bidder conference to identify additional alternate vendors. B Submit a change request to use the alternate vendor C Review the contingency reserves D. Conduct a risk audit 供应商未按照约定日期交付产品时发生了—个问题。风险应对计划要求使用替代供应商,该供应商更为昂贵但是可以立即交付。项目经理下一步应该怎么做? A.召开投标人会议,识别另外的替代供应商。 B.提交一份变更请求,使用替代供应商。 C.审查应急储备。 D.开展风险审计。 PMP答案解析:实施应急计划要提交变更请求 PMP参考答案:B |