以下城市均已开通:
关闭
当前位置:PMP团购网 > PMP考试资料 > 正文

PMP考试每天一练-2019年PMP考试试题66

作/转载者:PMP团购网      发布时间:2019/6/3        点击: 186

PMP考试试题一:

Two hours before a product is deployed, a project team member discovers an error. The project manager applies a Temporary fix to meet the critical milestone. The project manager applied which of the following?

A. Contingency plan

B. Quantitative risk analysis

C. Workaround

D. Defect repair

产品部署前两个小时,项目团队成员发现一个错误。项目经理应用临时修复:满足关键里程碑。项目经理应用的是下列哪一项?

A.应急计划

B.定量风险分析

C.权变措施

D.缺陷补救

PMP答案解析:“项目团队成员发现一个错误”,这是发现了缺陷,PM应用了临时修复。这是PM应用了缺陷补救

PMP参考答案:D

PMP考试试题二

During a project's concept, prototype, development, and testing phases, additional funding is requested several times. After the product launch, the budget is updated and the project manager determines there is a negative cost variance (CV).Which of the following does this indicate?

A. Original budget is greater than the total project cost at completion.

B. Total cost of the project is greater than the planned value (PV).

C. Total increment a funding exceeded the original budget.

D. Earned value (EV) is greater than the actual cost (AC)

在项目的概念、原型、开发和测试阶段,多次请求提供额外资金。在发布产品后更新预算,项目经理确定成本偏差(CV)为负,这表明了下列哪一项?

A.原始预算大于完工时总项目成本。

B.项目总成本大于计划价值(PV)。

C.增加的总资金超出原始预算。

D.挣值(EV)大于实际成本(AC)。

PMP答案解析:CV=EV-AC,四个选项中,B的描述,接近CV为负这个描述

阅读本文的人还阅读了:
PMP是什么?
PMP考试有什么科目?
PMP考试三个月来得及吗?
广州PMP考试地点
上海PMP考试地点在哪里?
广州PMP考试地点在哪里?
深圳PMP考试地点在哪里?

留言讨论区
我也来说两句


获取更新

合作与联系

友情链接: PMP培训团购网 安徽成考网 建工团购网 项目管理者联盟 pmp百科 磨石建筑教育 SPC培训 企业管理培训 清晖PMP培训 光环国际 青岛旅行社
PMP团购导航
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
东北PMP团购
其他城市团购
远程PMP团购
PMP团购网
免费领PMP团购券