PMP考试试题一:

When scheduling a project, the project manager has enough information to detail the project’s first phase. At the start of the project's execution, the project manager assumes that detailed schedules for the next phases will be created after more information is available. Which scheduling technique is the project manager using?

A. Iterative life cycle

B. Decomposition

C. Rolling wave planning

D. Adaptive life cycle

制定项目的进度计划时,项目经理拥有足够的信息,来详细说明项目第一阶段进度计划。在开始项目执行时,项目经理认为在获得更多信息后将制定下一阶段的详细进度计划。项目经理采用了哪一项进度安排技术?

A.迭代生命周期

B.分解

C.滚动式规划

D.适应性生命周期

PMP答案解析:题意描述比较符合滚动式规划的工作形式

PMP参考答案:C

PMP考试试题二

Miday through a project’s execution, a customer requests additional functionality that will be critical from a business perspective. Which of the following subsidiaries of the project management plan will be primarily impacted?

A.Configuration management plan

B.Scope management plan

C.Risk management plan

D.Communications management plan

在一个项目执行中途,客户要求增加从业务前景上看非常关键的功能。这将主要影响到以下哪一个项目管理计划附件?

A.配置管理计划

B.范围管理计划

C.风险管理计划

D.沟通管理计划

PMP答案解析:客户要求增加范围,主要影响范围管理计划,其次是配置管理计划

PMP参考答案:B

阅读本文的人还阅读了:
PMP报名时间是哪天?
PMP考点在哪里?
PMP认证费用多少?
PMP认证多少钱?
重庆PMP考试地点在哪里?
珠海PMP考试地点在哪里?
东莞PMP考试地点在哪里?
保定PMP考试地点在哪里?
杭州PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库