PMP考试每天一练-2019年PMP考试试题29

转载者:PMP团购网      发布时间:2019/3/20        点击: 2797

PMP考试试题一:

A project management office (PMO) is presented with three project choices for implementation. Project A has an internal rate of return (IRR) of 12%, project B has a schedule performance index (SPI) of0.8, and project C has a benefit-cost ratio (BCR) of 1:2.Based on this information, which of the following projects should be pursued?

A.Project B

B.Projects C and B

C.Project A

D.Project C

项目管理办公室(PMO)有三个项目可供选择实施。项目A的内部收益率(IRR)为12%,项目B的进度绩效指数(SPI)为0.8,项目C的效益-成本比(BCR)为1:2。根据这个信息,应选择实施下列哪一个项目?

A.项目B

B.项目C和B

C.项目A

D.项目C

PMP答案解析:项目B进度延误,项目C的BCR小于1.推荐项目A,内部收益率通常与银行利率相比,高于当期利率即可选

PMP参考答案:C

PMP考试试题二

An approved strategic plan allocates US$15 million to a building renovation project. The senior executive for the project.What should the project manager do next?

A.Update the project charter

B.Update the stakeholder register

C.Update the risk register

D.Update the risk management plan

一个已批准的战略计划向一个建筑翻新项目分配了1500万美元。项目高级主管离开公司,且任命了新的高级主管。项目经理下一步该怎么做?

A.更新项目章程

B.更新干系人登记册

C.更新风险登记册

D.更新风险管理计划

PMP答案解析:原高级主管离开公司,认命了新的高级主管,干系人发生了变化

PMP参考答案:B

阅读本文的人还阅读了:
深圳PMP考试地点在哪里?
香港PMP考试地点在哪里?
青岛PMP考试地点在哪里?
潍坊PMP考试地点在哪里?
长春PMP考试地点在哪里?
哈尔滨PMP考试地点在哪里?
重庆PMP考试地点在哪里?
珠海PMP考试地点在哪里?
东莞PMP考试地点在哪里?
保定PMP考试地点在哪里?
PMP考试报名怎么做?
国内PMP考试通过率有多高?
PMP考试有题库吗?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库