PMP考试每天一练-2019年PMP考试试题23
PMP考试试题一: During a project’s testing phase, the project team learns of a software tool that could have reduced the project’s development effort by40 days. Where should this be recorded A. Procurement documents B. Project or phase closure documents C. Lessons learned knowledge base D. Change log 在项目的测试阶段,项目团队得知一款软件工具能够减少项目的开发工作40天时间。这些应记录在哪里? A.采购文件 B.项目或阶段收尾文件 C.经验教训知识库 D.变更日志 PMP答案解析:无论是团队生成的经验教训还是团队获取的经验教训,都属于经验教训知识库 PMP参考答案:C PMP考试试题二 During a team meeting, the project manager collects information for the project charter. Which of the following will be included in the project charter? A.Assumptions and constraints, high-level risks, and stakeholder list B.Project purpose, summary budget, and project management plan C.Scope baseline, team composition, and project management plan D.Assumptions and constraints, work breakdown structure, and summary budget 项目经理在团队会议上收集项目章程信息。下列哪一项应包含进项目章程 A.假设和制约因素、高层次风险以及干系人名单 B.项目目的、预算汇总和项目管理计划 C.范围基准、团队构成和开支限制 D.假设和制约因素、工作分解结构和预算汇总 PMP答案解析:项目章程中没有项目管理计划,排除B。章程中也没有 C,排除 C。章程中没有工作分解结构,排除D PMP参考答案:A |