PMP考试每天一练-2018年PMP考试试题165
PMP考试试题一: A project that is 25% complete has a budget at completion of US$100,000, and an actual cost of US$50,000. Assuming that the remaining work will be performed at the same cost performance index incurred, what is the project’s estimate at completion? A.US$200,000 B.US$150,000 C.US$125,000 D.US$75,000 一个已经完成25%的项目完工预算为100000美元,而实际成本为50000美元。假设剩余工作将按已发生的相同成本绩效指数执行,则项目的完工估算是多少? A.200000美元 B.150000美元 C.125000美元 D.75000美元 PMP答案解析:典型偏差,CPI=EV/AC=(25%*10W)/5W=0.5,EAC=BAC/CPI=10W/0.5=20W PMP参考答案:A PMP考试试题二 A project team identifies the risks within the project. Which of the following techniques should the project team use? A.Assess risk priorities B.Review lessons learned C.Perform a sensitivity analysis D.Gather data and representations 项目团队识别了项目当中的风险。项目团队应使用下列哪一项技术? A.评估风险优先级 B.审查经验教训 C.执行敏感性分析 D.收集数据和展示 PMP答案解析:识别风险后,需要进行风险定性分析。C和D是风险定量分析的技术 PMP参考答案:A |